Austin Hills Golf Resort is a Singaporean-owned company that spent millions in trying to rectify problems caused by the landslide. Due to further complication of issues on underground water, soil erosion etc., things got out of hand and exacerbated the situation.
Seeing the situation got worsen, MBJB interfered and team-up with Austin Hills to conduct a join study on the affected area and concluded that an amount of RM4.5million is needed to resolve the problem. They have submitted the requisition to the Ministry of Housing and Local Government to allocate the needed amount and they promise to act immediately once the money has been distributed.
Friday, August 24, 2007
Mount Austin Landslide 茂奥斯丁土崩事件
Posted by Ahli Parlimen Tebrau - Teng Boon Soon柔佛州地不老区国会议员邓文村 at 00:55
Subscribe to:
Post Comments (Atom)
3 comments:
土崩事件已经拖了3年了,整条山坡已严重倾斜,土质松软,地低水流已导至部分马路也垄起,马路也因工程的关系被逼封路,路中央推满了大石头和黄泥。这一带的工业者,商家,来往福林园,SETIA INDAH,JP PERDANA居民等被逼绕道而行,生意每越下况。去年年尾和今年年头发生大水灾都让这里的厂家心惊胆跳,求神拜佛土崩别又再倒塌。政府不能坐视不理,把一切责任推在土地拥有人身上而不顾人民的安危。是否要等到有人在土崩事件里丧生才重视呢?请尽快拨款吧!
国会议员已经通过新山市议会申请拨款。计划中,维修的费用总共四百五十万。目前,只等待有关方面的批准公函。我们每一个星期都有跟有关方面接洽,希望能早日动工。对公众人士所造成的不便。多多包含。谢谢。